Hello Patch Manager Forum -
I just met with our Patching Team and they have a few questions. We might not be using things correctly or these maybe features coming down the pipe.
Automated Patching Tasks - What we are looking for is for Patches in Task 1 to complete and verify they are completed and then patching moves on to Task 2. Right now it is a manual process that we have to end up waiting for Task 1 to complete before we hit Task 2.
Patch Manager Web Console - We also discussed prestaging tasks and setting up role based access so we can have application owners patch their own systems. But I think we would need some kind of web console to do this.
Thanks -Dave