Hi all, SolarWinds is new to me and about to perform my first upgrade, I'm looking at the NPM Administrator guild which doesn't mention procedures when you have additional poller engines. So this is what I'm planning, let me know if this correct.
1. Stop additional Poller Servers (3 in my environment)
2. Login to main SW server using local windows account and run NPM-v10.5 Full.exe file
3 Bring up the 4 Poller Servers and run NPM-v10.5-Poller.exe on each of the poller servers.
4. There's a core-2013.1-hotfix1.zip in the full zip file installation but it mentions only to install it if I experience the problems.