      My question is that if we are monitoring any server ABC. that server ABC have three different databases running. Two DBs have scheduled unmanage for 2 week. when we are scheduling the unmanage on the ABC server for next 2 hrs it is overriding the unmanage for the 3 databases also. is there any way if we can schedule the permanent blackout that will not get override with the unmanage/manage of the ABC server. please suggest.